A change order is the signed amendment that adds, removes, or swaps work on a construction job and resets the price and the finish date to match. Sign one before the extra work starts. Download this change order form free in Word or PDF, or fill it in and sign it online with your contractor or client.

Free to use. Legally binding under the ESIGN Act, UETA, and eIDAS.Updated November 2026 by Document eSign
CHANGE ORDERReady to sign online.SignatureSigned and datedSIGN
or download a copy
Overview

What this template is

A change order is a written amendment to a construction contract. Once the job is underway, something changes: the owner wants a second window in the den, the demo crew opens a wall and finds rotted framing, the inspector asks for a larger beam, or the tile you picked is backordered for 10 weeks. The original contract does not cover any of that. A change order does. It describes the new or deleted work, states what it costs and how that cost was worked out, shows the contract price before and after, moves the completion date if the work takes longer, and says when the money is paid. Both the owner and the contractor sign it before the changed work begins. That last point is the whole reason the document exists. Without it, you end up with a contractor who believes a conversation in the driveway approved 4,000 dollars of extras, and an owner who believes the same conversation was a question. This template keeps a running total, so every change order shows the original price, the net effect of earlier changes, and the new price, and anyone reading change order number 6 can see where the job stands without digging out the first five.

Who uses it

A homeowner adding scope to a remodel halfway through, such as an extra outlet run, a pocket door, or an upgraded tileA general contractor who hit a concealed condition behind a wall and needs the owner's written approval and a price before opening it up furtherA small builder keeping a running ledger of changes on a custom home so the final invoice matches what was signedA commercial tenant or landlord changing a fit-out after the drawings were pricedA roofing, HVAC, or plumbing contractor swapping a specified product for an available one and adjusting the priceAn owner's representative or architect who wants every change priced and dated before work proceeds
What's inside
  • A reference block tying the change order to the contract date, job number, project address, and earlier change orders
  • The origin of the change: who asked for it, when, and why (owner request, hidden site condition, design change, inspector, substitution)
  • Separate lines for work added, work deleted, and work substituted, with Exhibit A for drawings, quotes, or photos
  • A pricing basis you pick: lump sum, time and materials with a not-to-exceed cap, or unit price, plus a cost breakdown
  • A running contract-price ledger: original price, earlier changes, price before, this change, and the new total
  • A time adjustment with the old and new completion dates and any milestone that moves
  • How the change is paid: next progress payment, a deposit, a revised schedule, or a credit, with retainage treatment
  • A choice between full settlement of the change and a written reservation for costs not yet agreed
  • Permit, inspection, and code responsibility for the changed work
  • A no-work-before-signature clause with a narrow emergency exception, and signature fields for owner and contractor
HOW IT WORKS

From template to signed in three steps.

01

Start from the template

Open it in the editor with the fields already mapped, or download the DOCX to edit offline.

02

Add signers and send

Drop signature and date fields, then route each party in order or in parallel.

03

Get a sealed copy

Everyone signs, and you get a tamper-evident PDF plus an audit certificate.

Start signing free

Free forever. No credit card. Your recipients sign with no account.

The details

Everything to know before you send it.

1

How to fill it in

Do it before the work, not after. A change order written up two weeks later from memory is a negotiation. One signed on the day of the request is a record.

  • Number every change order in sequence and list the earlier ones in clause 1. Gaps in the numbering are the first thing anyone checks in a dispute.
  • Clause 2: say who asked for the change and why. Owner-requested extras, hidden conditions, and inspector demands get treated differently in many contracts, so the reason matters.
  • Clause 3: describe the work so a crew that never heard the conversation could build it. Name the location, the quantity, and the product if the brand matters. Attach the quote or sketch as Exhibit A.
  • Clause 4: pick one pricing basis and delete the other two. If you use time and materials, always fill in the not-to-exceed amount.
  • Clause 5: carry the numbers forward from the last change order. The new contract price on this form should be the prior contract price on the next one.
  • Clause 6: write a number of days even when the answer is zero. A blank here invites a later delay claim.
  • Clause 8: choose Option A or Option B. Leaving both in means nobody knows whether the change is settled.
  • Sign it, send both parties a copy, and file it with the contract.
2

A filled-in example

Here is how the numbers work on a real-looking job. Every name and figure below is invented. Dana Ortiz hired Redline Renovations under a contract dated 2 March 2026 to remodel the kitchen at 77 Birch Court for 48,500 dollars. Change Order 1 added under-cabinet lighting for 1,200 dollars. During demo, Dana decided to move the island sink 3 feet toward the window, which meant a new drain and vent run under the slab edge and a GFCI receptacle on the island. Redline priced it as Change Order 2 the same afternoon.

  • Pricing basis: lump sum. Labor 18 hours at 85 dollars, which is 1,530 dollars. Materials 640 dollars. Plumbing subcontractor 950 dollars. Subtotal 3,120 dollars. Overhead and profit at the 10 percent the contract allowed, 312 dollars. Total 3,432 dollars.
  • Contract price ledger: original 48,500. Earlier changes add 1,200. Price before this change order 49,700. This change order adds 3,432. New contract price 53,132 dollars.
  • Time: plus 4 calendar days, moving completion from 15 May to 19 May 2026.
  • Payments: added to the next progress payment, due at cabinet install.
  • Clause 8: Option A, so 3,432 dollars and 4 days settle the change completely. Both signed on 24 March, and the plumber started the next morning.
3

Pricing the change: lump sum, time and materials, or unit price

Use a lump sum whenever the work is defined well enough to price. It is the easiest for the owner to approve and the hardest to argue about later, because the number is the number. Time and materials fits work nobody can see yet, like chasing rot behind siding until you reach solid wood. The risk sits with the owner there, so the not-to-exceed cap in clause 4 is not optional in practice: once the contractor nears the cap, the work stops until a new change order raises it. Unit pricing suits repeatable quantities, such as square feet of drywall replaced or linear feet of trench, where the rate is clear but the final count is not. Whatever you pick, ask for the breakdown. A single figure with no labor, material, or markup split is impossible to check, and it is the line owners most often challenge at the final invoice. Deductive change orders deserve the same care. When work is removed, the credit should reflect what the contractor actually saves, and clause 5 says so unless you agree a different figure.

4

Change order vs contract amendment vs punch list

All three come up near the same conversations, and they are not interchangeable. A change order is a contract amendment built for construction: it changes the scope of work and prices it, with the running contract total, the completion date, and the payment schedule that construction jobs need. A general contract amendment changes terms in any kind of agreement, such as a new term length, a different notice address, or a revised fee in a services deal, and it does not carry a price-and-time ledger. Use that for non-construction contracts. A punch list changes nothing. It records work the contract already required that is unfinished or defective, and the contractor fixes those items at no extra cost. The test that sorts them is simple: was this work in the deal on day one? If yes and it is not done right, it goes on the Punch List. If no, it needs a change order. For the paperwork around a job, the Subcontractor Agreement covers trades hired by the contractor, a Work Order handles a single repair call, a Statement of Work defines scope for project-based services, and the Certificate of Completion records that the job is finished.

5

What the law says about change orders

Most private jobs are governed by the contract itself, so the change clause in your contract comes first: read it for notice deadlines and who can approve a change. Some states add rules on top, especially for home improvement work. California is a clear example. Business and Professions Code section 7159(d) requires a home improvement contract and any changes to it to be in writing and signed by the parties before the work covered by the change order begins, and section 7159(c)(5) says a change-order form becomes part of the contract only if it is written and signed before that work starts. Section 7159.6(a) makes an extra work or change order unenforceable against the buyer unless it states the scope of the work, the amount added to or subtracted from the contract, and the effect on the progress payments or the completion date. Section 7159.6(b) bars the buyer from requiring extra work without written authorization, and 7159.6(c) still lets a contractor recover for work actually performed under unjust-enrichment remedies. Clauses 3, 5, 6, 7, and 10 of this template map to those requirements. Federal construction contracts run on the FAR Changes clause, 48 CFR 52.243-4. It lets the contracting officer order changes within the general scope of the contract by a written change order, and paragraph (e) gives the contractor 30 days after receiving the order to assert its right to an adjustment in writing. Paragraph (d) also limits recovery for an informal change, other than one caused by defective specifications, to costs incurred no more than 20 days before the contractor gave written notice, which is a useful reminder on private jobs too: raise the change in writing the day it happens. Other states have their own home improvement statutes, so check yours before you rely on this form for residential work. Sources: Cal. Bus. and Prof. Code sections 7159 and 7159.6 (as amended through Stats. 2025, ch. 585), and 48 CFR 52.243-4 (eCFR).

6

Where change orders go wrong

Verbal approvals cause most change order fights. The owner says yes in the hallway, the crew builds it, and the bill arrives as a surprise. Clause 10 stops that by keeping the work on hold until both signatures are on the page. Time is the next trap. Contractors price the money and forget the days, then ask for an extension at the end of the job when every change is already signed with a blank in the time box. Owners should want that box filled too, because an unstated delay is the one that gets argued about later. Third, the running total goes missing. If each change order shows only its own amount, nobody knows the current contract price until someone adds up a folder of paper. Clause 5 carries it forward every time. Last, watch the reservation language. A contractor who signs Option A has settled that change for good, including delay costs. If the full impact is not known yet, Option B is the honest choice, with a deadline for the follow-up claim.

7

Signing, records, and when to get advice

A change order is an ordinary contract amendment, so it needs no notary or witness, and both sides can sign it electronically. Under the federal ESIGN Act, 15 U.S.C. 7001(a), a signature, contract, or other record relating to a transaction in or affecting interstate commerce may not be denied legal effect solely because it is in electronic form. Signing online also gives you a timestamp, which helps prove the change order was signed before the work began. Keep every signed change order with the contract, the drawings, and the photos, in number order. This page is general information, not legal advice. Talk to a construction attorney if a large change is disputed, if the contractor stopped work over an unsigned change, or if a lien or claim deadline is approaching, because those deadlines come from your contract and state law.

Disclaimer

This template and the guidance on this page are provided for general information only and are not legal advice. Laws differ by country and state, so review the final document against your own situation and have a qualified lawyer check anything high-value or regulated before you sign.

FAQ

Questions, answered.

What is a change order in construction?

It is a signed amendment to a construction contract that adds, deletes, or substitutes work and adjusts the contract price, the completion date, or both. The owner and the contractor sign it before the changed work starts, and it becomes part of the contract.

Who signs a change order?

The owner and the contractor, at minimum. If the contract names an architect or owner's representative with approval authority, they often sign too. Check your contract for who is allowed to approve a change, because a signature from someone without authority may not bind the owner.

Can a contractor charge for extra work without a signed change order?

It depends on the contract and the state. Many contracts say unsigned extras are not payable. In California, Business and Professions Code 7159.6 makes an unsigned or incomplete change order unenforceable against the buyer, but still allows recovery for work actually performed under unjust-enrichment remedies. The safe course for both sides is to sign before the work.

What should a change order include?

A description of the changed work, the pricing basis and breakdown, the amount added or deducted, the new contract price, any change in the completion date, and how the change affects payments. Number it in sequence and attach any drawings or quotes it relies on.

Can a change order reduce the contract price?

Yes. A deductive change order removes work and credits the owner. The credit should match what the contractor actually saves on the deleted work, including any agreed markup, and it should show in the running contract total just like an addition.

What if the owner orders a change before the price is agreed?

Some contracts let the owner direct a change first and settle the price later, usually on time-and-materials records. If yours does not, use this form with time and materials pricing and a not-to-exceed cap, sign it, and replace the estimate with the final figure on a follow-up change order.

Is the change order form available in Word format?

Yes. Download the change order form as a Word (.docx) file and edit it in Microsoft Word, Google Docs, or Pages. Copy the cost lines for as many items as the change needs. You can also download a PDF or fill it in and sign online.

Can I download the change order form as a PDF?

Yes. A print-ready PDF is available alongside the Word version, which works well on a clipboard at the job site. Download either one free, or fill it in and sign online without downloading anything.

Live in under a minute

Ready to send your first envelope?

Create your free forever account, upload a document, and send it for signature in minutes. No credit card required.

30 free envelopes a month Legally binding · global Audit trail on every document