How to fill it in
Do it before the work, not after. A change order written up two weeks later from memory is a negotiation. One signed on the day of the request is a record.
- Number every change order in sequence and list the earlier ones in clause 1. Gaps in the numbering are the first thing anyone checks in a dispute.
- Clause 2: say who asked for the change and why. Owner-requested extras, hidden conditions, and inspector demands get treated differently in many contracts, so the reason matters.
- Clause 3: describe the work so a crew that never heard the conversation could build it. Name the location, the quantity, and the product if the brand matters. Attach the quote or sketch as Exhibit A.
- Clause 4: pick one pricing basis and delete the other two. If you use time and materials, always fill in the not-to-exceed amount.
- Clause 5: carry the numbers forward from the last change order. The new contract price on this form should be the prior contract price on the next one.
- Clause 6: write a number of days even when the answer is zero. A blank here invites a later delay claim.
- Clause 8: choose Option A or Option B. Leaving both in means nobody knows whether the change is settled.
- Sign it, send both parties a copy, and file it with the contract.