How to fill it in
Fill the project and walkthrough blocks before you start walking, then log items as you go. Use one row per defect. If a room has three problems, that is three items, not one line that says "fix bedroom".
- Project block: copy the contract date and job number exactly. If change orders were approved, list their numbers so everyone knows which version of the scope you are checking against.
- Walkthrough block: record who actually walked. If the architect or a key subcontractor was there, name them. Write down any area you did not inspect, such as an attic you could not reach, so nobody later claims it was approved.
- Location: be specific enough that a trade who was not there can find it. "Unit 4B, hall bath, left of vanity" works. "Bathroom" does not.
- Description: say what is wrong and what done looks like. "Grout missing at tub surround, bottom two rows, regrout to match" is an item someone can close.
- Responsible trade: name the subcontractor or trade, such as drywall, electrical, or painting. The contractor owns the list, but this column is how the work gets assigned.
- Target date: give each item its own date if timing varies, or leave the item blank and rely on the overall completion date in clause 4.
- Clause 7: pick Option A or Option B and delete the other. Leaving both in is the single fastest way to start a payment dispute.
- Sign it at the end of the walkthrough while both sides are standing there. Keep the final sign-off block blank until the last item is verified.